UPDATE: ACS Obtains Additional $13.6 Million for General Contractor Client After $19.2 Million Jury Trial Victory

In March 2022, ACS obtained a $19.2 million jury verdict in favor of its general contractor client after a lengthy trial against the project owner. Since that time, ACS has successfully obtained awards through post-trial motion practice for an additional $13.6 million in favor of the general contractor. These awards increased to total judgment to more than $32 million.

When moving to enter judgment on the jury verdict, ACS successfully argued for and obtained more than $5 million in prejudgment interest on the jury verdict to compensate the general contractor for having to go years without payment for work performed. ACS also successfully obtained a decree of foreclosure on its construction lien and incorporated language in the judgment requiring the owner to pay an additional $1.9 million in Washington State sales tax on the jury award. Finally, under the authority of the Washington construction lien statute (RCW 60.04.181), ACS sought to recover the attorneys’ fees, costs, and expenses incurred by the general contractor client during the course of litigation. ACS succeeded in obtaining an award for more than $6.6 million for various expenses and costs including ACS’s attorney fees, all the costs of hiring expert witnesses, costs and expenses related to subcontractors’ presentation of pass-through claims against the owner, and other litigation costs and expenses.

Importantly, the $13.6 million recovered by ACS in post-trial motion practice means that the general contractor client is as close to being “made whole” as possible because it has been compensated for the time value of the money, taxes, and the litigation costs incurred to obtain the jury award. By diligently enforcing the Washington construction lien statute to the fullest extent, ACS has enabled its client to enjoy the full benefit of the jury’s $19.2 million award as payment for the work performed, as the jury intended.

Scroll to Top